Fibre Optic Subduct Installation in East London – Traffic Management
Project Skills Solutions recently completed a high-profile fibre optic subduct installation in East London. This project involved closing a lane and cycleway for a 200 m run between two server locations, requiring complex traffic management and technical expertise.
Client Challenge
The client needed four subducts installed through a new duct system that connected their premises, running 200 m from one server room to another. The route exited customer premises, ran under public road and cycle lane, then re-entered the site, demanding a higher degree of planning, equipment, and safety oversight.
Our Solution
With fully trained engineers holding New Roads and Street Works (NRSWA) qualifications. Our team of experienced and qualified telecommunications engineers worked closely with all relevant stakeholders—including local authorities, traffic management providers, and the client’s internal team—to ensure the project was delivered safely, compliantly, and on time. Project Skills Solutions provided a turnkey solution:
Traffic Management & Access Setup
– Coordinated lane and cycleway closure
– Installed barrier systems, signs, and traffic marshals
– Ensured compliance with highway regulations
Cable Handling & Subduct Works
– Utilised heavy cable drums, cable trailers, and winches
– Pulling subducts through new ductwork safely and efficiently
– Incorporated best practice techniques from industry standards
Execution & Safety
– Setting up traffic management and ensuring public safety
– Assessing existing ducts and ensuring clear routing
– Pulling in four 25 mm diameter subducts using winches to avoid manual strain
– Verifying route integrity with roping, clearing, and proving ducts
Client Benefits
– Minimized disruption by closing only one lane and cycleway
– Enhanced safety through qualified personnel and industry-standard traffic control
– Efficient installation with mechanical winches and cable trailers
– Full compliance with highways and street works legislation
Why Choose Project Skills Solutions?
Trained & Qualified Team
Our engineers hold New Roads and Street Works qualifications, ensuring safe and legal operations under traffic management.
Complete Project Delivery
From planning and traffic management to subduct installation and documentation, we project manage everything in-house.
Cost & Risk Reduction
Efficient planning and professional execution minimise public disruption and installation costs, delivering smooth, reliable results.
Get in Touch
Planning a fibre optic subduct installation that crosses public spaces? Contact Project Skills Solutions today for a clear, cost-effective, and compliant solution.